Highlights
- The new Pandemic Response Unit consists of a 8500 SQFT tent structure with 67 beds, four washrooms, medical rooms, nurse stations and janitor rooms.
- This tent was constructed in three weeks from start to finish.
- Botting completed the mechanical scope with two shifts on plumbing and sheet metal, working 10 days in a row.
- The mechanical portion consists of medical gas, domestic water, sanitary, natural gas and air distribution systems.